6-3. Freight Elevators and Vertical Material Conveyors (VMC)

This page is a comprehensive explanatory guide on the overview of freight elevators and vertical material conveyors (VMC) in logistics facilities, structure and merit comparisons, retrofitting construction periods and restrictions, and installation costs.

1. Overview and Legal Regulations of Freight Elevators

A freight elevator in a logistics facility is a fundamental transport equipment for vertically moving pallets, cage carts, and heavy items between floors. The biggest difference from other equipment like automated conveyors is that a worker (a person accompanying the load) can directly board it and perform loading/unloading tasks.

1.1 Main Features and Specifications

1.2 Related Legal Regulations and Procedures

Because freight elevators are strictly subject to application as "elevators" under the Building Standards Act and the Industrial Safety and Health Act, legal procedures and regular maintenance are mandatory.

Law / Regulation Required Obligations and Responses
Building Standards Act ・Building confirmation application at the time of new installation and completion inspection are mandatory.
・Obligation of an annual periodic inspection report (inspection by an architect, etc.).
Industrial Safety and Health Act ・For load capacities of 1.0t or more, an installation notification and performance inspection are required.
Fire Compartmentation (Building Law) ・The entire hoistway must be enclosed with fireproof walls, and fire dampers, fire shutters, or fire doors must be installed at entrances and exits.

2. Structure, Classification, and Introduction Merits of Vertical Material Conveyors (VMC)

A Vertical Material Conveyor (VMC) is a material handling equipment that fully automatically vertically elevates only cargo within a warehouse. Unlike a freight elevator, because it is designed with a structure that "absolutely prohibits people from riding," it is treated as a type of material handling equipment.

2.1 Basic Structure and Flow of Operation

An "elevating carrier (loading platform)" is built into the inside of the hoistway, and it automatically links with conveyors placed at the entry and exit ports on each floor.

  1. Automatic Carry-in: A worker or AGV places the cargo (pallet, cage cart, etc.) on the waiting conveyor.
  2. Safety Interlock Confirmation: The shutter closes, and it automatically detects a safe state where there are no people inside the hoistway.
  3. High-Speed Vertical Elevation: The carrier ascends or descends to the destination floor at high speed (2 to 3 times the speed of an elevator).
  4. Automatic Discharge: Upon arrival at the destination floor, it automatically pushes out and discharges to the receiving entry/exit conveyor.

2.2 Main Classifications and Types

Classification by Elevation Method

Classification by Transport Layout

Compatible Types by Cargo Shape

2.3 Comparison Between Freight Elevators and Vertical Material Conveyors (VMC)

Comparison Item Freight Elevator Vertical Material Conveyor (VMC) Merits of Introducing VMC
Human Boarding / Legal Positioning Possible (Building Standards Act "Elevator") Strictly Prohibited ("Transport Equipment (Machine)") Physically blocks the risk of human bodily accidents.
Confirmation Application / Statutory Inspection Mandatory (Confirmation application / Annual inspection) Unnecessary (Exempt from administrative procedures) No confirmation application procedures or examination period needed, shortening construction time.
Transport Capacity / Speed Medium (Speed limits exist because people ride) Very High (Continuous conveyor transport) Eliminates cargo waiting time and significantly improves transport capacity.
Material Handling Linkage Manual entry/exit is primary Full linkage with AGV/AMR and Automated Warehouses Connects with transport lines allowing for complete unstaffed operation.

2.4 Demerits and Precautions of VMC

3. Retrofitting Construction and Installation Restrictions for Existing Warehouses

When retrofitting a Vertical Material Conveyor (VMC) or a freight elevator into an existing logistics warehouse, "the necessity of a building confirmation application," "creating an opening in the existing floor (slab)," and "securing a vertical passage area" are the main points of consideration.

3.1 Retrofitting Construction Comparison Summary

Item Freight Elevator (Retrofit) Vertical Material Conveyor (VMC / Retrofit)
Construction Period (On-site construction period) Approx. 2 months to 4 months Approx. 2 weeks to 1 month
Overall Lead Time Half a year to 8 months (Several months for application/consultation) 2 months to 3.5 months (Application unnecessary)
Legal Examination / Procedures Building confirmation application is mandatory Unnecessary (Only equipment notification)
Pit (Underfloor excavation) A deep pit (1.2m to 1.5m or more) is necessary A thin pit (about 30cm) or pit-less (slope installation) is possible
Restrictions on Existing Building Treated as an extension, recalculation of floor-area ratio and building coverage ratio may be required Can be processed as "equipment installation" with only an opening in the existing floor

3.2 Main Installation Restrictions and Hurdles in Retrofitting Construction

  1. Floor Slab Opening and Structural Reinforcement: Because pillars and main structural beams cannot be cut, openings can only be made in positions avoiding existing beams. When cutting the concrete floor, noise, vibration, and dust occur, and reinforcing steel materials must be assembled around the opening.
  2. Securing the Pit (Excavation on the lowest floor): For elevators, digging a pit deeper than 1m below the floor causes interference with underground beams to be a constraint, whereas VMCs can be of "pit-less specifications (slope installation)," giving them a high degree of freedom for retrofitting.
  3. Measures for Penetrating Fire Compartments: Because it is an opening spanning across floors, the hoistway must be enclosed with fireproof walls, and there is an obligation to newly install automatic closing fire shutters or fire doors at the entrances and exits.

3.3 Precautions for Warehouse Operation During Construction (Construction While Operating)

4. Installation and Maintenance Cost Comparison and Judgment Criteria

This is a comparison of the initial costs (main unit + construction costs + architectural/application fees) and running costs involved in introducing a freight elevator versus a vertical material conveyor (VMC).

4.1 Initial Cost Comparison Summary (Load capacity 1.5t-2.0t, 3-story building, lift height 10m-15m approx.)

Cost Item Freight Elevator Vertical Material Conveyor (VMC) Factor of Cost Difference
Equipment Main Unit Price 12 million to 18 million yen 15 million to 22 million yen VMCs come with front and rear conveyors and safety control devices, making the main unit expensive.
Architectural / Application Fees 2 million to 4 million yen 0 yen (Unnecessary) Elevators require building confirmation applications and periodic reporting compliance.
Hoistway / Fireproofing Work 3 million to 6 million yen 1.5 million to 3 million yen Elevators require strict fireproof structures and pit excavation.
[Total] Initial 17 million to 28 million yen 16.5 million to 25 million yen Overall initial cost is slightly cheaper to equivalent for VMC.

4.2 Comparison of Running Costs (Maintenance Costs)

Item Freight Elevator Vertical Material Conveyor (VMC)
Statutory Periodic Inspection Cost Mandatory (Once a year, approx. 100k-200k yen/year) Unnecessary (No obligation for statutory inspection)
Maintenance Inspection Contract High (Approx. 500k-1M yen annually) Cheap to Standard (Approx. 300k-600k yen annually)
Electricity Costs / Repairs Standard (High frequency of replacing safety mechanisms) Parts replacement according to operating frequency

4.3 Criteria for Deciding Which to Choose