Work Throughput Capacity for 100% Inspection and Packing
Models an operational team of 4 inspection operators and 1 assistant.
Required work space expands or contracts based on roll-box cart dimensions and operational methods.
Calculation Example:
Executing 100% inspection on 20,000 piece items per hour.
Processing rate = 2.0 seconds per inspected piece item.
1 set of 4 operators processes 1 piece item every 0.5 seconds.
Hourly processing capacity per set = 3,600 / 0.5 = 7,200 pieces.
Required sets = 20,000 / 7,200 = 2.8 sets => 3 sets.
Required area = 13 m² * 3 sets = 39 m².