This document explains statutory regulations, structural specifications, and simulation mechanisms involved in "Building Area Calculation" for logistics centers.
Subsection 1 Total Logistics Space Area and Area Adjustments
Constructing a distribution center involves site selection governed by statutory zoning restrictions. City Planning Acts alone divide land into 13 zoning classifications (residential, commercial, industrial, etc.). Combined with Building Standards Acts, Fire Services Acts, Radio Wave Acts, and community relations, site selection requires professional expertise.
Site selection mandates knowing required land plot area (or building footprint area). Outsourcing this externally incurs time and cost, requiring internal site surveys to set baseline premises.
While Tera Calculation 2 primarily teaches methods to calculate logistics space area scale from shipping data, software estimating land plot area is included to support site selection planning. These calculated figures serve as preliminary reference estimates; final site confirmation requires adjusting estimates against detailed engineering parameters.
Only licensed architects can produce formal construction drawings. While non-licensed professionals cannot finalize building specifications, establishing clear visual concepts of distribution center floor areas and scale is both possible and necessary.
Building diagrams shown in Tera Calculation 2 represent conceptual models, not architectural blueprints. Dimensions serve strictly as temporary parameters to estimate approximate floor areas.
Subsection 1 Building Aspect Ratios
Abstract space area summaries lack physical dimensions. Specifying building aspect ratios derives physical length and width dimensions. Square 1:1 or 2:1 footprints are rare; rectangular 3:2 or 4:3 shapes are widely adopted for distribution centers.
Subsection 2 Exterior Walls, Columns, and Firewalls
Columns require structural strength (material, thickness, dimensions). In multi-story distribution centers, exterior walls also serve as load-bearing structural walls. Consequently, post-construction walls cannot be easily altered to add door openings.
Default Tera Settings model 200 mm exterior walls, 700 × 700 mm single-story columns (increasing by 100 mm per additional floor), spaced at 10 m column spans.
Projected building footprint areas are calculated based on wall centerlines (100 mm inward for 200 mm walls).
Modifying Tera Settings for wall thickness, column spans, or firewall thickness dynamically updates floor area calculations.
Subsection 3 Floor Slabs, Beams, and Elevation Dimensions
Ground floors model 1,000 mm raised docks, with story clear heights set to 7,000 mm above floor level. Floor slab + beam depth is modeled as 1,000 mm to calculate story heights.
Subsection 4 Multi-Story Buildings and Canopies
Canopies provide weather protection over loading docks. Facilities with 3 or more stories rarely feature external canopies, adopting internal drive-in dock bays (termed Built-in Bay format in Tera Calculation).
50% of canopy footprint area is added to projected building footprint. Building Coverage Ratio = (Projected Footprint + Canopy Area × 50%) / Plot Site Area.
Subsection 5 Emergency Stairwells and Freight Elevators
Facilities with 2 or more stories require adding floor area for emergency stairwells and freight elevators.
Tera Calculation models firewalls every 1,500 m² of gross floor area, adding 1.5 m wide emergency stairwells and freight elevators (2.3 × 2.3 m elevator shaft × 1.5 sets) per 1,500 m² section.
Subsection 6 Main Building and Detached Pallet AS/RS
Normally, a distribution center consolidates into a single unified building.
However, automated warehouses are occasionally constructed as separate "rack buildings" (rack structures with exterior cladding attached directly to racking frameworks without separate building columns). Though rare, because this impacts site layouts (especially driveway aisle widths), it is incorporated into Tera Calculation 2.
Automated warehouses utilize high vertical bay counts to maximize ROI. Integrating high-bay AS/RS into multi-story main buildings creates multi-story floorless void spaces, which is structurally and financially disadvantageous.
Deciding whether to build an AS/RS as a detached structure or integrate it into the main distribution center building represents a key strategic evaluation.
Subsection 7 Computing 40 Building Type Patterns
40 building type patterns combine: Detached AS/RS (2 options) × Story Count (Up to 5 floors) × Canopy Presence (2 options) × Dock Bay Placement Sides (2 options) = 40 combinations. Calculates floor areas and dimensions across all 40 patterns, exportable as an Excel summary table. The Plot Site Area screen derives building data directly from this matrix table.