Logistics Data Analysis Methods, Procedures, and Utilization To Menu_

jp | eng | tw ___ By Logistics Technology Institute

Current Status Survey Data (Preconditions)

Survey Item Sheet for Distribution Center System Design

This document contains the basic survey items required for designing a distribution center system. Items already submitted do not need to be re-entered. Please add items corresponding to your company's specific characteristics as necessary.

1. Project Overview

  1. Project Name: Proposal Title ( )
  2. Customer Name: Customer Name ( ) / Department in Charge, Contact Person, TEL, FAX
  3. Delivery Location & Target Completion Date: Delivery Location ( ) / Scheduled Completion Date (Year/Month)
  4. Desired Submission Date & Estimate Level: Submission Deadline (Year/Month/Day) / Estimate Type (Rough / Detailed)
  5. System Content & Scope: Scope handled by our company & equipment specifications
  6. Project Purpose (Motivations): Logistics improvement, automation, new construction, relocation, etc.
  7. Proposal Scope (Estimate Scope): Scope of equipment, construction, WMS, operational software, etc.
  8. Customer Budget: Logistics Equipment Budget (───── Thousand JPY) / Information System Budget (───── Thousand JPY)
  9. Availability of Provided Documents: Site/Building drawings, current layout, data for analysis (FD/CSV, etc.), feasibility of field survey

2. Building Overview (Concept at Present)

  1. Classification: New Construction / Existing Facility
  2. Site Area, Building Coverage Ratio, Floor Area Ratio: Site Area (───── ㎡), Building Coverage Ratio (── %), Floor Area Ratio (── %)
  3. Restrictions, etc.: Height Restrictions (Yes/No ── m), Sunlight Restrictions (Yes/No)
  4. Borrowed Drawings: Site drawings, building floor plans, building elevation plans (Possible / Not Possible)
  5. Building Specifications: Steel Structure ── Stories, Floor-to-Ceiling Height (Clear height under beams ── m)
  6. Installed Facilities: Elevator specifications, Power capacity (Unused portion ── kW)
  7. Floor Specifications per Story: Load Capacity (── t/㎡), Finishing Accuracy, Floor Cross-Section Diagrams
  8. Modification / Removal of Existing Equipment: (Yes / No)
  9. Construction Schedule (Planned): Time schedule for architectural and equipment construction
  10. Construction / Design Company Contact: Company Name in Charge / Inquiry Feasibility

2-1. Functions by Area (Floor)

Please fill in the basic concept and handling units for each floor and zone.

Area Division Area (㎡) Floor Handling Unit Supplementary Description / Equipment
Inbound Dock / Berth PL / Case / Piece / Loose
Inbound / Inspection / Staging Area PL / Case / Piece / Loose
Floor Storage Area PL / Case / Piece / Loose
Pallet Rack Storage / AS/RS PL / Case / Piece / Loose
Medium/Light Duty Racks, Carousel, Flow Racks PL / Case / Piece / Loose
Logistics Processing Area (Value-Added Services) PL / Case / Piece / Loose Labeling, kitting, etc.
Inspection & Packing Area PL / Case / Piece / Loose
Outbound Staging / Outbound Dock PL / Case / Piece / Loose
Office (Inbound/Outbound Reception, Computer Room) ─
Vertical Conveyor, Conveyor, Freight Elevator PL / Case / Piece / Loose Elevator load capacity, quantity, etc.

3. Cargo Volume Survey

3-1. Product Characteristics (including raw materials and secondary materials)

3-2. Overview of Inbound Characteristics

3-3. Inventory Characteristics, Shipping Characteristics, and Operating Conditions

【Inventory Characteristics】

【Shipping Characteristics】

【Staff Composition & Working Hours】

4. Information Systems

4-1. Order Receiving Method

4-2. Shipping Instruction Method